Here is what was accomplished this week:
- framers did some added work, put the wood bucks around the doors and windows, and did some rework,
- windows were installed,
- rear sliders were installed,
- HVAC duct work was installed, along with the plenum, zone dampers, and wiring,
- moisture proof board was installed at knee walls in the garage and above the guest bath,
- vents / chimney holes were cut in the roof and the exterior vents installed,
- bath fan boxes were installed,
- roofers finished the shingles
- tyvek paper was installed on wood portions of the exterior,
- HV electrical was about 75% roughed in.
I think it was good progress for this week.
Sunday, August 5, 2007