Sunday, August 12, 2007

Week 9 - Week of 8/06/2007

This week the following happened:
- The house voltage electrical rough-in was completed,
- The low voltage (telephone, cable, internet, door bell, house number) electrical rough-in was completed,
- The master bath tub was installed,
- The tailored foam was injected in the block walls,
- Framing punch (do overs) was done,
- Truss inspection was done,
- The electric service was pulled and a meter set, so we now have power at one 110V box on the side of the house.

We're still waiting for the correct guest bath tub, so the plumbing rough-in can be completed and then the rest of the inspections done.

No comments: