Sunday, July 29, 2007

Week 7 - Week of 7/23/2007

Progress seemed slow this week. The gas lines were about 80% roughed in. Some plumbing repair work was done and about 80% of the plumbing rough-in was done. The front door was installed. HVAC ductwork installation started. Roof shingles are about 90% completed. Truss inspection was completed and approved.

Also, several "do-overs" were completed. The master bath shower valve plumbing was fixed. The refrigerator ice maker line was fixed. The "buck" for the Nook slider was removed and the block shaved to the correct size.

There are still some framing "do-overs", along with some remaining block / concrete "chip outs" to be done. Also, the gas stub-out for the generator needs to be done correctly.

Hopefully next week will bring greater progress.