This week the following construction events were completed:
1 The under slab sewer and plumbing lines were installed. Pressure testing commenced.
2 The water meter was installed.
3 A connection was made to the public sewer system.
4 We had our initial "Builder" meeting to review the home plans and options.
5 Added fill dirt was placed inside the forms.
6 The area for some of the footers was dug out.
7 Rebar to reinforce part of the footings and tie to the concrete block walls was delivered to the site.
8 A Porta-Potty was placed on the site.
9 A "form board survey" was completed and sent to the city for review.
10 Pringle sent me a Notice of Commencement to sign, have notarized, and return. This is for the screen cage, which is outside the house perimeter and apparently requires a separate document. We returned this.
11 Cliff, our Builder, notified the inspectors that an inspection would be needed next Tuesday before the slab could be poured.
Friday, June 22, 2007
Friday, June 15, 2007
Week 1 - Week of June 11, 2007
This is one of a series of blogs about our experience in designing / building a house and making it our home in a new development in Mount Dora, Florida during the 2004 - 2007 time period.
This section provides weekly summaries of what was completed during construction. For more information, see http://lakesofmountdora.org .
Our Construction Start Date was to be June 18, 2007. However, construction started a few days early, on June 12, 2007.
This week the following construction events happened:
1 Permit box posted, with Building Permit and plan set.
2 lot staked for the lot corners and the house footprint.
3 Three dumpsters were delivered to the front of the lot.
4 The forms for the slab were set.
5 The density of the dirt within the forms was inspected.
This section provides weekly summaries of what was completed during construction. For more information, see http://lakesofmountdora.org .
Our Construction Start Date was to be June 18, 2007. However, construction started a few days early, on June 12, 2007.
This week the following construction events happened:
1 Permit box posted, with Building Permit and plan set.
2 lot staked for the lot corners and the house footprint.
3 Three dumpsters were delivered to the front of the lot.
4 The forms for the slab were set.
5 The density of the dirt within the forms was inspected.