Here's what happened during the third week of construction:
- The pipes were covered with dirt,
- Reinforcement rebar was put in the footer / pier area,
- The vapor barrier under the slab was put down / sealed,
- Electrical conduit was put down for floor outlet, etc.,
- The city inspections were done,
- My private inspection was done and problems corrected,
- The slab was poured,
- The forms were removed,
- The slab was saw cut for controlled cracking.