This week the following construction events were completed:
1 The under slab sewer and plumbing lines were installed. Pressure testing commenced.
2 The water meter was installed.
3 A connection was made to the public sewer system.
4 We had our initial "Builder" meeting to review the home plans and options.
5 Added fill dirt was placed inside the forms.
6 The area for some of the footers was dug out.
7 Rebar to reinforce part of the footings and tie to the concrete block walls was delivered to the site.
8 A Porta-Potty was placed on the site.
9 A "form board survey" was completed and sent to the city for review.
10 Pringle sent me a Notice of Commencement to sign, have notarized, and return. This is for the screen cage, which is outside the house perimeter and apparently requires a separate document. We returned this.
11 Cliff, our Builder, notified the inspectors that an inspection would be needed next Tuesday before the slab could be poured.
Friday, June 22, 2007
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment