This is one of a series of blogs about our experience in designing / building a house and making it our home in a new development in Mount Dora, Florida during the 2004 - 2007 time period.
This section provides weekly summaries of what was completed during construction. For more information, see http://lakesofmountdora.org .
Our Construction Start Date was to be June 18, 2007. However, construction started a few days early, on June 12, 2007.
This week the following construction events happened:
1 Permit box posted, with Building Permit and plan set.
2 lot staked for the lot corners and the house footprint.
3 Three dumpsters were delivered to the front of the lot.
4 The forms for the slab were set.
5 The density of the dirt within the forms was inspected.
Friday, June 15, 2007