Sunday, September 23, 2007

Week 15 - Week of 9/17/2007

Here's what happened during the 15th week of construction:
  • The floor and bathroom tile installation was completed
  • The cabinets arrived and were installed, less a few problems
  • The concrete flatwork was done (walks, driveway, patio, pads)
  • The garage doors and door openers were installed
  • The window labels were removed and a first wash was done
  • The installation of the decorative accent stone was completed
  • We met with our builder to discuss solutions to a few issues, including a door location and the kitchen island cabinets. Pringle is very accommodating on problem resolution.

No comments: