Here's what happened during Week 13 of construction:
- On Labor Day, the crew worked on drywall mudding and taping. All the drywall work got finished this week,
- Some minor electrical punch list items got fixed,
- The exterior painting was done,
- Interior doors and trim were delivered,
- Interior doors were hung, trim around doors was installed,
- Baseboard was installed in the rooms that will have carpet,
- Corian windowsills were installed,
- The interior paint was delivered,
- My outside inspector did a pre-painting inspection and found only one minor issue.
Good progress for the week.