Sunday, October 7, 2007

Week 17 - Week of 10/01/2007

Here's what happened during the 17th week of construction:

- countertops were installed
- water heater was hung and plumbed
- sink faucets and drains were installed
- whole house water filter was installed
- toilets were set
- screen cage was installed
- electrical outlets, switches, and trim plates were installed
- interior and exterior light fixtures were installed,
- smoke detectors were installed,
- water heater control was installed (but in wrong location)
- cooktop and oven were delivered and set temporarily in place
- acrylic knockdown base for the lanai and porch was put down
- closet and pantry shelving was installed
- mirrors were installed

No comments: